Phoenix Approves $44M Agreement with MGC Contractors for Lift Station 40 Rehabilitation Near Ray Road and I-10

  • When: 2025/03/26
  • Address: Near Ray Road and the I-10 Freeway, Phoenix, AZ
  • City: Phoenix
  • State: AZ
  • Category: Infrastructure Development
  • Subcategory: Water/Sewer
  • Asset Class: Land
  • Property Type: Covered Land & Land Banking
  • Size: $44,162,034.72 total contract value; construction scope includes wet well, electrical building, biofilter, chemical storage, and site expansion

On March 26, 2025, the Phoenix City Council approved Ordinance S-51740, authorizing a design-bid-build contract with MGC Contractors, Inc. for the rehabilitation of Lift Station 40. The project includes constructing a new wet well, submersible pumps, pig launching stations, an electrical building, standby generator, biofilter odor control, chemical storage, and associated electrical and control infrastructure. It also covers site expansion, installation of new water lines for fire hydrants, and demolition of the existing lift station. The project, located near Ray Road and I-10, is valued at up to $44,162,034.72 and will proceed over a 960-day contract term. Although the bid exceeded the estimated project cost, it was deemed reasonable and remains within the approved budget. The project will be funded through the city’s Water Services Capital Improvement Program budget.

Why it Matters

This major infrastructure investment ensures continued wastewater management capacity and reliability in a growing district. It replaces aging systems and supports future development and environmental standards.

Source

Applicant - City of Phoenix Water Services Department


Ownership - City of Phoenix


Developer - MGC Contractors, Inc.


Allowed Uses: Rehabilitation of public wastewater infrastructure, including construction of a new wet well, pig launching stations, electrical systems, and demolition of the old facility. Supports ongoing city wastewater management operations.